Roberts Bank Terminal 2 (RBT2)

Also called RBT2, Roberts Bank Terminal 2 project, Roberts Bank Terminal

Proponent: Vancouver Fraser Port Authority (VFPA).

Major Projects Office page

No photograph is published on the Major Projects Office page.

Why it is listed

Federal proponent. Federal proponent: Vancouver Fraser Port Authority (VFPA)

led by the project proponent – Vancouver Fraser Port Authority (VFPA)Source, read Oct. 3, 2026
Proponentled by the project proponent – Vancouver Fraser Port Authority (VFPA)Source, read Oct. 3, 2026

Status

On August 28, 2026, Canada provided notice in the Canada Gazette that the Governor in Council may amend Schedule 1 of the Building Canada Act to list the RBT2 project as a project of national interest.Source, read Oct. 3, 2026

Roadmap

Roadmap for Roberts Bank Terminal 2 (RBT2)time not statedtime not statedFederal approval with 370legally binding conditionsApril 20, 2023Final permits pendingnot estimatedVFPA and GCT sign MOUApril 21, 2026−1 mo2 moReferred to Major ProjectsOfficeJuly 16, 2026Listing consultations beginJuly 2026Canada Gazette notice ofpotential listingAug. 28, 2026Governor in Council listingdecisionnot estimated
  • Done
  • Current step
  • Not yet reached
  1. Federal approval with 370 legally binding conditionsDone

    April 20, 2023

    On April 20, 2023, following an environmental assessment conducted by an independent Review Panel, the Government of Canada approved the RBT2 project, subject to 370 legally binding conditions.Source, read Oct. 3, 2026
  2. Final permits pendingCurrent step

    Time from the previous step is not stated.

    Date not stated. Not estimated: fewer than five projects date both this step and the previous one.

    RBT2 completed a federal impact assessment in 2023, received key environmental approvals, and is pending final permits.Source, read Oct. 3, 2026
  3. VFPA and GCT sign MOUDone

    Time from the previous step is not stated.

    April 21, 2026

    On April 21, 2026, the VFPA and GCT entered into a Memorandum of Understanding to explore partnership to advance RBT2 at the Port of Vancouver.Source, read Oct. 3, 2026
  4. Referred to Major Projects OfficeDone

    3 months after the previous step.

    July 16, 2026

    On July 16, 2026, the Government of Canada officially referred the RBT2 project to the MPO and initiated the process to consider listing it under the Building Canada Act.Source, read Oct. 3, 2026
  5. Listing consultations beginDone

    about 1 month earlier than the previous step.

    July 2026

    In July 2026, MPO began consultations with Indigenous communities, the provincial government, and with federal permitting departments, as a part of the process towards assessing the potential listing of RBT2Source, read Oct. 3, 2026
  6. Canada Gazette notice of potential listingDone

    About 2 months after the previous step.

    Aug. 28, 2026

    On August 28, 2026, Canada provided notice in the Canada Gazette that the Governor in Council may amend Schedule 1 of the Building Canada Act to list the RBT2 project as a project of national interest.Source, read Oct. 3, 2026
  7. Governor in Council listing decisionNot yet reached

    Time from the previous step is not stated.

    Date not stated. Not estimated: fewer than five projects date both this step and the previous one.

    with the intent for the Minister of One Canadian Economy to make a recommendation for Governor in Council decision.Source, read Oct. 3, 2026

Funding

FundingThe federal government will invest in infrastructure upgrades to Roberts Bank Terminal, expanding the capacity of the Port to ship to new export markets overseas.Source, read Oct. 3, 2026

Laws named in the sources

Building Canada Act

The MPO has initiated the process for the potential listing of RBT2 under the Building Canada Act (the Act).Source, read Oct. 3, 2026

The project is listed or considered under this act. Bills that name it are linked below.

Bills

Sources