Major project · British Columbia

North Coast Transmission Line

Also called NCTL, North Coast Transmission Line (NCTL) Project

Proponent: BC Hydro.

Major Projects Office page
Photo: Major Projects Office

Photo: Major Projects Office

Why it is listed

Federal funding. Federal funding stated: loan

The Canada Infrastructure Bank (CIB) has reached financial closed on a $139.5 million loan to BC Hydro to support the early works phase of the North Coast Transmission Line (NCTL) project.Source, read Oct. 3, 2026
ProponentBC Hydro has proposed the NCTL to expand energy infrastructure by building new transmission linesSource, read Oct. 3, 2026

Status

On September 3, 2026, Minister Hodgson and Minister Robertson, alongside Premier Eby announced the start of construction for Phase 1 of the project.Source, read Oct. 3, 2026

Roadmap

Roadmap for North Coast Transmission Line−1 mo8 moReferred to Major ProjectsOfficeNov. 13, 2025CIB loan for early worksNov. 2025$3.9 billion committed underCanada-B.C. agreementJuly 2, 2026Phase 1 construction beginsSept. 3, 2026
  • Done
  • Current step
  1. Referred to Major Projects OfficeDone

    Nov. 13, 2025

    On November 13, 2025, the project was referred to the Major Projects Office (MPO).Source, read Oct. 3, 2026
  2. CIB loan for early worksDone

    about 1 month earlier than the previous step.

    Nov. 2025

    In November 2025, the Canada Infrastructure Bank (CIB) provided a $139.5-million loan to BC HydroSource, read Oct. 3, 2026
  3. $3.9 billion committed under Canada-B.C. agreementDone

    About 8 months after the previous step.

    July 2, 2026

    Under the agreement, the Government of Canada and the Province of British Columbia are committing $3.9 billion toward phases 1 and 2 of the projectSource, read Oct. 3, 2026
  4. Phase 1 construction beginsCurrent step

    2 months after the previous step.

    Sept. 3, 2026

    On September 3, 2026, Minister Hodgson and Minister Robertson, alongside Premier Eby announced the start of construction for Phase 1 of the project.Source, read Oct. 3, 2026

Funding

  • $139.5 million Loan
  • $3.9 billion Funding

No over-budget estimate. These are the commitments the official pages state. None is an original budget set beside a later cost for the same work.

LoanThe Canada Infrastructure Bank (CIB) has reached financial closed on a $139.5 million loan to BC Hydro to support the early works phase of the North Coast Transmission Line (NCTL) project.Source, read Oct. 3, 2026
FundingWe will provide $3.9 billion, through various tools, toward the total capital costs of Phases 1 and 2 of this projectSource, read Oct. 3, 2026

Laws named in the sources

No law is named on the official pages read for this project.

Bills

No bill in the database names this project, or an act it is listed or considered under.

The framework law for the major projects list is below. It does not name this project.