Major project · Saskatchewan

McIlvenna Bay Project

Also called McIlvenna Bay Foran Copper Mine Project, McIlvenna Bay copper-zinc mine

Proponent: Eldorado Gold Corporation.

Major Projects Office page
Photo: Eldorado Gold

Photo: Eldorado Gold

Why it is listed

Federal funding. Federal funding stated: funding

In December 2024, Natural Resources Canada provided up to $20 million through the Critical Minerals Infrastructure Fund (CMIF) — now the First and Last Mile Fund — to McIlvenna BaySource, read Oct. 3, 2026
ProponentOn April 14, 2026, Eldorado Gold Corporation completed acquisition of Foran Mining Corporation, officially taking ownership of the McIlvenna Bay project.Source, read Oct. 3, 2026

Status

The project is now ramping up toward full commercial production.Source, read Oct. 3, 2026

Roadmap

Roadmap for McIlvenna Bay Project4 yr5 moProvincial environmentalassessment approval2022Referred to Major ProjectsOfficeSept. 11, 2025Construction about 88% completeJan. 31, 2026time not statedFirst copper concentrateproducedJune 2026Commercial productionnot estimated
  • Done
  • Not yet reached
  • Not stated
  1. Provincial environmental assessment approvalDone

    2022

    In 2022, the McIlvenna Bay Project underwent a provincial environmental assessment, and received provincial approval.Source, read Oct. 3, 2026
  2. Referred to Major Projects OfficeDone

    About 4 years after the previous step.

    Sept. 11, 2025

    On September 11, 2025, the project was referred to the Major Projects Office (MPO).Source, read Oct. 3, 2026
  3. Construction about 88% completeNot stated

    5 months after the previous step.

    Jan. 31, 2026

    On February 19, 2026, the proponent reported that construction of the McIlvenna Bay Project was approximately 88% complete as of January 31, 2026.Source, read Oct. 3, 2026
  4. First copper concentrate producedDone

    About 4 months after the previous step.

    June 2026

    In September 2026, the McIlvenna Bay project celebrated several milestones, including producing its first copper concentrate in June 2026, followed by its first zinc concentrate in July 2026.Source, read Oct. 3, 2026
  5. Commercial productionNot yet reached

    Time from the previous step is not stated.

    Date not stated. Not estimated: fewer than five projects date both this step and the previous one.

    is expected to reach commercial production in the third quarter of 2026.Source, read Oct. 3, 2026

Funding

  • $20 million Funding
  • $41 million Funding
  • $156 million Funding

No over-budget estimate. These are the commitments the official pages state. None is an original budget set beside a later cost for the same work.

FundingIn December 2024, Natural Resources Canada provided up to $20 million through the Critical Minerals Infrastructure Fund (CMIF) — now the First and Last Mile Fund — to McIlvenna BaySource, read Oct. 3, 2026
FundingIn January 2025, Innovation, Science and Economic Development Canada (ISED) provided $41 million through the Strategic Innovation Fund to integrate innovative clean technologies at the McIlvenna Bay site.Source, read Oct. 3, 2026
FundingIn May 2025, the Canada Growth Fund agreed to commit approximately $156 million alongside co-investors to support the development and construction of the McIlvenna Bay Project.Source, read Oct. 3, 2026

Laws named in the sources

No law is named on the official pages read for this project.

Bills

No bill in the database names this project, or an act it is listed or considered under.