Major project · Québec

Contrecoeur Container Terminal Project

Also called Contrecœur Terminal Container Project, Contrecoeur Expansion Project, Contrecœur Container Terminal Project, Contrecœur terminal expansion

Proponent: Montreal Port Authority.

Major Projects Office page
Photo: Major Projects Office

Photo: Major Projects Office

Why it is listed

Federal proponent. Federal proponent: Montreal Port Authority

Montreal Port AuthoritySource, read Oct. 3, 2026
ProponentMontreal Port AuthoritySource, read Oct. 3, 2026

Status

On August 14, 2026, the Montreal Port Authority announced the start of in-water construction work for the Contrecoeur Expansion Project, marking a major milestone and the beginning of a key construction phase for the future container terminal.Source, read Oct. 3, 2026

Roadmap

Roadmap for Contrecoeur Container Terminal Projecttime not stated18 dFederal environmentalassessment completeddate not statedReferred to Major ProjectsOfficeSept. 11, 2025MOU signed by MPO, CIB andMontreal Port AuthoritySept. 29, 20257 d3 moPreparatory work begins;in-water works contract awardedOct. 9, 2025Fisheries Act authorization(offsetting plan)Oct. 16, 2025Second Fisheries Actauthorization (in-water works)Jan. 5, 20263 d4 moCIB financing finalizedApril 6, 2026Start of construction announcedApril 9, 2026In-water construction beginsAug. 14, 20263 yrPhase 2 construction2027Full operations targeted2030
  • Done
  • Current step
  • Not yet reached
  1. Federal environmental assessment completedDone

    Date not stated

    The project has undergone a comprehensive environmental assessment conducted by the Impact Assessment Agency of Canada, including public and Indigenous consultations.Source, read Oct. 3, 2026
  2. Referred to Major Projects OfficeDone

    Time from the previous step is not stated.

    Sept. 11, 2025

    On September 11, 2025, the project was referred to the Major Projects Office (MPO).Source, read Oct. 3, 2026
  3. MOU signed by MPO, CIB and Montreal Port AuthorityDone

    18 days after the previous step.

    Sept. 29, 2025

    On September 29, 2025, the Major Projects Office, the Canada Infrastructure Bank, and the Montreal Port Authority signed a Memorandum of Understanding (MOU) with the common goal of advancing the Contrecoeur Container Terminal Project.Source, read Oct. 3, 2026
  4. Preparatory work begins; in-water works contract awardedDone

    10 days after the previous step.

    Oct. 9, 2025

    On October 9, 2025, the Port of Montreal began preparatory work for the expansion and awarded the contract for in-water works of the future container terminalSource, read Oct. 3, 2026
  5. Fisheries Act authorization (offsetting plan)Done

    7 days after the previous step.

    Oct. 16, 2025

    On October 16, 2025, the Montreal Port Authority obtained a Species at Risk Act compliant Fisheries Act authorization from Fisheries and Oceans Canada (DFO)Source, read Oct. 3, 2026
  6. Second Fisheries Act authorization (in-water works)Done

    3 months after the previous step.

    Jan. 5, 2026

    On January 5,2026, the Montreal Port Authority obtained a second Species at Risk Act compliant Fisheries Act authorization from DFOSource, read Oct. 3, 2026
  7. CIB financing finalizedDone

    3 months after the previous step.

    April 6, 2026

    On April 6, 2026, the Canada Infrastructure Bank and the Montreal Port Authority finalized financing details.Source, read Oct. 3, 2026
  8. Start of construction announcedDone

    3 days after the previous step.

    April 9, 2026

    On April 9, 2026, the Government of Canada announced the start of construction of the project.Source, read Oct. 3, 2026
  9. In-water construction beginsCurrent step

    4 months after the previous step.

    Aug. 14, 2026

    On August 14, 2026, the Montreal Port Authority announced the start of in-water construction work for the Contrecoeur Expansion Project, marking a major milestone and the beginning of a key construction phase for the future container terminal.Source, read Oct. 3, 2026
  10. Phase 2 constructionNot yet reached

    About 5 months after the previous step.

    2027

    with Phase 2 expected to begin in 2027Source, read Oct. 3, 2026
  11. Full operations targetedNot yet reached

    About 3 years after the previous step.

    2030

    full operations targeted for 2030.Source, read Oct. 3, 2026

Funding

  • $1.16 billion Loan
  • $130 million Funding
  • $150 million Funding

No over-budget estimate. These are the commitments the official pages state. None is an original budget set beside a later cost for the same work.

Loanthe Canada Infrastructure Bank (CIB) is supporting the new Contrecoeur container terminal by loaning $1.16 billion to the Montreal Port Authority (MPA).Source, read Oct. 3, 2026
FundingThe project is supported by contributions from the Government of Québec ($130 million), Transport Canada ($150 million)Source, read Oct. 3, 2026

Laws named in the sources

Impact Assessment Act

Environmental monitoring mechanisms are in place to ensure compliance in accordance with the Impact Assessment Act, the Fisheries Act, and the Species at Risk Act.Source, read Oct. 3, 2026

Fisheries Act

Environmental monitoring mechanisms are in place to ensure compliance in accordance with the Impact Assessment Act, the Fisheries Act, and the Species at Risk Act.Source, read Oct. 3, 2026

Species at Risk Act

Environmental monitoring mechanisms are in place to ensure compliance in accordance with the Impact Assessment Act, the Fisheries Act, and the Species at Risk Act.Source, read Oct. 3, 2026